Australia's Snowy 2.0 hydro project now expected to cost up to A$25 billion
2017 estimate
A$2 billion
Now
A$22.5 to A$25 billion
The estimate has grown from A$2 billion at the 2017 announcement to between A$22.5 billion and A$25 billion for completion in 2029.
What went wrong
The update blames the contractor's underestimate of the work, missed productivity targets and rising equipment and labour costs. The project is no longer on a fixed-price contract.
Planned storage
350,000 MWh
The pumped hydro plant is to provide 2,200 megawatts and 350,000 megawatt-hours of storage as backup for days of low wind and sun.